Page 216 - BA2 Integrated Workbook - Student 2017
P. 216

Chapter 14





                           Payback





               2.1   Payback technique

               The payback technique considers the time a project will take to pay back the money
               invested in it. It is based on expected cash flows. To use the payback technique a
               company must set a target payback period.

                           Decision criteria

                               Compare the payback period to the company's target return time and
                                if the payback for the project is quicker the project should be
                                accepted.


                               Faced with mutually exclusive projects choose the project with the
                                quickest payback.







               Go over illustration 1

               Try TYU 2