TEST 3 - COSTING


                                      Costing variances










             • When absorption costing is applied: Under- or over-


                  recovery of overheads = Volume variance + Expenditure

                  variance.


             • When variable costing is applied: Under- or over-recovery


                  of overheads = Expenditure variance.

                    • The volume variance is not applicable when variable


                          costing is applied.

             • An adverse volume variance means that actual production


                  volume is less than the budgeted allocation base used.


             • A favourable volume variance: actual production volume is

                  more than the budgeted allocation base used.







                                                                                                                                   39