Chapter 12









                   Example 4 cont.




                   Workings

                   (W1) Contract profit

                                                                       $m         $m
                   Contract price                                                  30

                   Costs to date                                        14
                   Costs to complete                                     7

                                                                      ——
                                                                                  (21)

                                                                                 ——
                   Contract profit                                                  9

                                                                                 ——



                   (W2) Stage of completion
                   Cost basis: cost to date/total cost                14/21     66.7%



                   (W3) Contract asset                                            $m

                   Cost to date                                                    14
                   Profit to date                                                   6
                   Received from customer                                         (12)

                                                                                 ——

                                                                                    8
                                                                                 ——