                                            ABC – example 1













             (b) Activity based costing



             Total number of production runs:




             Product A =  (550 / 110) = 5 production runs

             Product B = (110 / 55) = 2 production runs




             Total machine setup hours:




             Product A =  7 hours per production run x 5 production runs = 35 setup hours
             Product B = 2 hours per production run x 17.5 production runs = 35 setup hours

             Total machine set up hours = 35 + 35 = 70 setup hours