Supplementary objective test questions




               10.3 A construction contract is in its early stages and the overall outcome is
                     uncertain. Surveyors estimate that the work is 5% complete. Costs incurred to
                     date are $100,000 and 50% of the costs are deemed to be recoverable from the
                     customers. The total contract price is $3,000,000.

                     Which of the following statements is true regarding the accounting
                     treatment of this contract as per IAS 11?

                     A     Revenue of $150,000 will be recorded in the SOPL

                     B     Revenue of $100,000 will be recorded in the SOPL

                     C     Revenue of $50,000 will be recorded in the SOPL


                     D     No revenue should be recorded for this contract