Accounting for materials





                            Systems of inventory control






               3.1  Re-order level

               This level will be determined with reference to the time it will take to receive an order
               and the possible inventory requirements during that time.  When this level of
               inventory is reached a new order must be placed to prevent stock outs.

                           Re-order level = maximum usage × maximum lead time


                           Re-order level = (maximum usage × maximum lead time) + buffer







                  Example 1





                   A business uses 5,000 units of raw material per week and it takes 3 weeks to
                   receive the goods after the order has been placed.  The business also keeps
                   additional inventory of 2,500 units in reserve.

                   Calculate the re-order level.

                   5,000 units × 3 weeks + 2,500 buffer inventory = 17,500 units








                  Test your understanding 2




                   The demand for a particular product is expected to vary between 10 and 50
                   units per day.  Lead time is, on average, 5 days, although it has been as short
                   as 3 days and as long as 10 days.  The company orders 1,500 units a time.
                   The company operates a 300-day year.

                   Calculate the re-order level