Page 352 - F2 - MA Integrated Workbook STUDENT 2018-19
P. 352

Chapter 14




               To calculate the IRR:

                    Calculate two NPVs for the project at two different costs of capital. The higher
                     the discount rate – the lower the NPV will be.


                    Use the following formula to find the IRR:


                                                 N L
                             IRR  =    L +     ———  (H – L)
                                              N L – N H


               where: L = lower discount rate

                       H = higher discount rate

                       NL = NPV at the lower discount rate


                       NH = NPV at the higher discount rate.