                            Target Costing




                             Target Costing is a proactive cost control system. The target cost is
                             calculated by deducting the target profit from a pre-determined selling
                             price based on customers’ views.


                 Step 1: A target price is set, based on the customers’ perceived value of the
                               product. This will therefore be a market based price.



                  Step 2: The required target operating profit per unit is then calculated. This
                        may be based on either return on sales or return on investment.



                   Step 3: The target cost is derived by subtracting the target profit from the
                                                      target price.




                                      Step 4: The cost gap is then calculated.




                   Step 5: If there is a cost gap, attempts will be made to close the gap with
                 techniques such as value engineering which will look at every aspect of the
                                           value chain business function.