Chapter 15
Labour variances
5.1 Calculations
AHAR
Rate variance
AHSR Total variance
Efficiency variance
SHSR
If there is idle time, the rate variance is based on the hours actually paid whilst the
efficiency variance is based on the hours actually worked.
Idle time variance:
Actual hours worked × standard rate per hour X
Actual hours paid × standard rate per hour Y
–––––
Idle time variance this is always adverse X – Y
–––––
Illustrations and further practice
Now try TYU question 6 from Chapter 15.