Page 176 - Microsoft Word - 00 CIMA F1 Prelims STUDENT 2018.docx
P. 176
Chapter 10
The high-low method
2.1 Step by step process
This is a method of breaking semi-variable costs into their two components.
A semi-variable cost being a cost which is partly fixed and partly variable.
Step 1 Find the variable cost per unit
Increase in cost
=
Increase in activity
Step 2 Find the fixed cost
= Total cost – (variable cost per unit × activity level)
Step 3 Calculate the expected cost
172