Page 3 - CIMA MCS Workbook May 2019 - Day 1 Suggested Solutions
P. 3
SUGGESTED SOLUTIONS
What does Jord insist on … Jord requires that customers ensure all conveyancing work is
before the design phase complete prior to the design phase commencing (page 9)
commences?
What restrictions are placed … A house cannot leave the factory for on‐site construction until it
on a completed house has been signed off by a senior quality assessor (page 10)
leaving the factory for on‐
site construction?
How long does full assembly … Full assembly of the external house structure is normally
of the external house take? complete within five to ten working days (page 11).
What does the personal Jord …Jord construction manager is constantly present during this
construction manager do whole on‐site erection phase, in order to coordinate and control all
during on‐site construction? aspects of the work carried out on site (page 11)
What are customers who …if the customer decides to manage the build process themselves
decide to manage the build then the customer takes full responsibility for project management
process themselves of the build (page 12)
responsible for?
What is core to Jord’s … Jord’s quality approach and professionalism is core to its
competitive advantage? competitive advantage (page 13)
How much does a Jord home …C$6000 per square metre (page 13)
cost per square metre?
What percentage of the …22% (page 14)
total build is attributable to
external completion and
landscaping for a Jord
home?
Per the mission statement, …to continuously improve our service to customers, by being
How does Jord intend to totally responsive to their needs and by constructing sustainable,
improve its service to bespoke and high‐quality buildings, through a process of
customers? consultation and innovation (page 16)
How does Jord attempt to … Jord invests in continual staff training and the reward and
mitigate the loss of quality development scheme is considered one of the best in the
staff? industry(page 17)