Chapter 13





                           Project control





               3.1   Three stages in project control

                    Select performance measures and set targets for these.


                    Assess performance at project gateways. A project should not be allowed to
                     proceed unless it successfully passes through the gateway

                    Take corrective action if out of control.


               3.2   Possible corrective action


                    Fast tracking.

                    Crashing.

                    Adding additional resources.

                    Scope reduction.

                    Adopting higher risk but potentially more efficient approaches.


                    Employee motivation.

               If the project manager believes that corrective action will not be successful then
               he/she should consider abandoning the project (in the exam you may be asked to
               evaluate this decision from a financial point of view).




                  Illustrations and further practice


                  Now try TYU question 2.