PROJECT AND RELATIONSHIP MANAGEMENT (E2) ‐ PRACTICE TASKS

                  Task


                  To: Finance Manager
                  From: Finance Director
                  Date: Today
                  Subject: Risk Management

                  I attach for your attention an email I have just received from the Production Director.

                  We currently have several contracts with new supermarkets in the tender stage. If they decide to
                  look closely at our risk management procedures we must be sure to be able to demonstrate a
                  clear responsibility for risk management within GRAPPLE and a robust process in place.

                  This is also likely to entail changes to procedures, perhaps even the creation of a separate team.
                  We will need to be sure that the need for these changes is fully understood by all those affected.

                  I need to advise him of our views in advance of the next board meeting. Can you look at two
                  specific areas for me and prepare some notes for our discussion:

                  Firstly, how GRAPPLE could improve its risk management process? Secondly, how might we
                  manage change with introducing any of the new processes and potentially even a new
                  department?



                  Thanks
                  David


                  Prepare the work that the Finance Director has requested            (45 minutes)









































                  KAPLAN PUBLISHING                                                                    39
   14   15   16   17   18   19   20   21   22   23   24