Page 6 - CIMA MCS Workbook November 2018 - Day 2 Suggested Solutions
P. 6

CIMA NOVEMBER 2018 – MANAGEMENT CASE STUDY

               The  difference  between  the  results  of  the  two  appraisals  will  indicate  the  overall  risk  levels
               involved.

               Apply more difficult targets


               When  performing  investment  appraisals,  comparison  will  be  made  of  the  project  results  to  a
               target figure.  In NPV calculations the target cost of capital is incorporated into the calculations
               themselves.   For  other  appraisal  tools  such  as  payback  or  accounting  rate  of  return  (ARR),  an
               arbitrary target is set by management.

               Projects  that  meet  or  beat  these  targets  are  deemed  to  be  acceptable.   If  we  know  that  the
               figures used in the appraisal are uncertain, one way of addressing this is to use a more difficult
               target, so add a couple of percentage points onto the cost of capital figure used or target ARR
               figure.  Shorten the payback period.  By making it more difficult for the projects to be accepted we
               are automatically incorporating a bit of a buffer to deal with the uncertainty faced.


               Sensitivity analysis

               Once a project appraisal such as an NPV calculation has been done, we can do extra calculations
               that allow us to identify figures critical to the success of the project.  We could also, for instance,
               increase all of our costs by 5% and look at how it affects the results, or reduce our sales volumes
               by 10% and see the effects.

               One way of using this  sensitivity analysis is to look at a particular variable and calculate by how
               much it would need to alter for us to change our minds about the decision to go ahead with the
               project or not.  Variables whose calculations produced a low sensitivity figure would be deemed
               to be critical ones, as only small changes in these variables would affect the overall feasibility of
               the project.

               For instance, if it was found that there was a 10% sensitivity to the extra sales volumes generated
               by  the  project  and  a  1%  sensitivity  to  the  material  cost  for  the  new  packaging  then  our  main
               concern would be that it only needs a 1% increase in material costs compared to the numbers
               we’ve predicted for the project to fail.  We would then need to investigate this further, aiming to
               either reduce the material cost or get more certainty about its potential cost.


               Simulation

               Simulation is sensitivity analysis done on a much larger scale, running the appraisal many times
               with different combinations of variables included to get an idea of the pattern of overall potential
               results.

               Note  that  all  of  these  techniques  will  allow  better  decisions  to  be  made  when  uncertainty  is
               involved but none of them will give an absolute go or no‐go decision about the project.  It will still
               come down to a professional decision that does involve risk being taken on.

               Finance Manager





               96                                                                  KAPLAN PUBLISHING
   1   2   3   4   5   6   7   8   9   10   11