10. USFD progress.
USFD TESTING PROGRESS UPTO THE MONTH OF Feb-2021
Sl. No. Items Details
1 Total length to be tested/ Month 244
2 Total yearly work load 2924
A RAIL 1990
a Cumulative target upto the month 1824.2
b Progress during the month 203
c Total progress up to the month 1787.5
B Bridge 71
a Cumulative target upto the month 65
b Progress during the month 0
c Total progress up to the month 71
C High banks and cuttings 272
a Cumulative target upto the month 249
b Progress during the month 0
c Total progress up to the month 175.5
D Curves 65
a Cumulative target upto the month 60
b Progress during the month 0
c Total progress up to the month 43
5 Point &Xings, SEJ's and scabs 146
a Cumulative target upto the month 134
b Progress during the month 42.5
c Total progress up to the month 77
E WELDS(AT/SKV+FBW) 380
a Cumulative target upto the month 348
b Progress during the month 50
c Total progress up to the month 429
3 Total (A+B+C+D+E) 2924
a Cumulative target upto the month 2680
b Progress during the month 295.5
c Cumulative Progress upto the month 2583.0