10. USFD progress.


         USFD TESTING PROGRESS UPTO THE MONTH OF Feb-2021


                     Sl. No.                        Items                              Details
                        1      Total length to be tested/ Month                         244
                        2      Total yearly work load                                   2924
                        A      RAIL                                                     1990
                        a      Cumulative target upto the month                        1824.2
                        b      Progress during the month                                203
                        c      Total progress up to the month                          1787.5
                        B      Bridge                                                    71
                        a      Cumulative target upto the month                          65
                        b      Progress during the month                                  0
                        c      Total progress up to the month                            71
                        C      High banks and cuttings                                  272
                        a      Cumulative target upto the month                         249
                        b      Progress during the month                                  0
                        c      Total progress up to the month                          175.5
                        D      Curves                                                    65
                        a      Cumulative target upto the month                          60
                        b      Progress during the month                                  0
                        c      Total progress up to the month                            43
                        5      Point &Xings, SEJ's and scabs                            146
                        a      Cumulative target upto the month                         134
                        b      Progress during the month                                42.5
                        c      Total progress up to the month                            77
                        E      WELDS(AT/SKV+FBW)                                        380
                        a      Cumulative target upto the month                         348
                        b      Progress during the month                                 50
                        c      Total progress up to the month                           429
                        3      Total (A+B+C+D+E)                                        2924
                        a      Cumulative target upto the month                         2680
                        b      Progress during the month                               295.5
                        c      Cumulative Progress upto the month                      2583.0