SUB FINAL PAY APPLICATION / RELEASE



      MAIL TO :          Angeles Contractor, Inc. (Attention: A/P)
                         8461 Commonwealth Avenue, Buena Park, CA 90621
      SUBCONTRACTOR NAME :
      SUB MAILING ADDRESS :

      PROJECT NAME :                                                       ACI PROJECT NO.  :
      PERIOD FROM  :                            TO :

     STATEMENT OF CONTRACT ACCOUNT
                 Item  1      Original Contract Amount                                  $
                 Item  2      Approved Change Order Amount (SCA Received)               $
                 Item  3      Adjusted Contract Amount (item 1 plus item 2)             $
                 Item  4      Value Of Work Completed To Date (Attach SOV Approved)     $
                 Item  5      Less Retention (10% of item 4)                            $
                 Item  6      Total Less Retention (item 4 minus item 5)                $
                 Item  7      Less Previous Certificates For Payment (item 6 from last pay app)  $
                 Item  8      Amount Due This Request (item 6 minus item 7)             $
                 Item  9      Balance To Finish, Including Retainage (item 3 minus item 6)  $

     CERTIFICATE OF SUBCONTRACTOR
     I hereby certify that the work performed and the materials supplied to date, as shown on the above, represent the actual value of accomplishment under the
     terms of the contract (and all authorized changes thereto) between the undersigned and relating to the above referenced project
     SIGNATURE OF SUBCONTRACTOR
     NAME & TITLE


         CONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT          AFFIDAVIT OF COMPLIANCE WITH CALIFORNIA PREVAILING
                     California Civil Code Section 8136           WAGE LAW, CALIFORNIA LABOR CODE SECTIONS 1720-1815
       NOTICE: THIS DOCUMENT WAIVES THE CLAIMANT'S LIEN,
       STOP PAYMENT NOTICE, AND PAYMENT BOND RIGHTS               The undersigned, being duly sworn, states that it is a Subcontractor for
       EFFECTIVE ON RECEIPT OF PAYMENT.  A PERSON SHOULD          Angeles Contractor, Inc. on the public project listed below, and has
       NOT RELY ON THIS DOCUMENT UNLESS SATISFIED THAT THE        complied with the provisions of the Cal. Labor Code Sections 1720-1815,
       CLAIMANT HAS RECEIVED PAYMENT.                             and has paid all employees the specified general prevailing rate of per
                                                                  diem wages to its employees, and any amounts due pursuant to Cal.
       Identifying Information                                    Labor Code 1813. Also, the Subcontractor has employed the required
       Name of Claimant:                                          number of apprentices on this project as required. In addition, the
                                                                  undersigned makes this sworn statement pursuant to Cal. Labor Code
       Name of Customer:  Angeles Contractor, Inc.                1775(b)(4) and 1777.7(d)(4).
       Job Location:
       Owner:                                                     The undersigned has also reviewed the payroll practices of each of
       Conditional Waiver and Release                             Subcontractor's lower-tiered subcontractors on this project. Each of
                                                                  subcontractor's lower-tiered subcontractors has paid the specified
       This document waives and releases lien, stop payment notice, contract  prevailing rate of wages to its employees, has paid any amount due
       rights, and payment bond rights the claimant has for labor and service  such employees under Cal. Labor Code 1813, has employed the
       provided, and equipment and material delivered, to the customer on this job.  required number of apprentices on this project, and has provided
       Rights based upon labor or service provided, or equipment or material  subcontractor with an affidavit that complies with Cal.
       delivered, pursuant to a written change order that has been fully executed by  Labor Code 1775(b)(4) and 1777.7(d)(4).
       the parties prior to the date that this document is signed by the claimant, are
       waived and released by this document, unless listed as an Exception below.
       This document is effective only on the claimant's receipt of payment from the  Name of Project:    __________________________________
       financial institution on which the following check is drawn:  Address of Project:__________________________________
       Maker of Check:  Angeles Contractor, Inc.
       Amount of Check:   $                                       I declare under penalty of perjury under the laws of the State of California
       Check Payable to:                                          that the foregoing is true and correct.
       Exceptions                                                 Executed this ______________ day of _________________, 20___
       This document does not affect any of the following:        _____________________________________________, California.
       Disputed claims for extras in the amount of:   $
                                                                  _____________________________________ (Subcontractor Name)
       Signature
       Claimant's Signature:                                      _____________________________________(Authorized Signature)
       Claimant's Title                                           _______________________________________ (Name & Title)
       Date of Signature:



                                                                                                         REV: 1.0.5  10/11/2012