Page 4 - Emergency Department Project, Soroka Medical Center_Neat
P. 4
As for the expansion of the Emergency Phase Three will include the reorganization of the units
Department, over the last several weeks within the Emergency Department and renovation and
the first stage of the expansion was refurbishing of existing interior areas, including the
successfully finished with the completion triage area, and their adaptation to the new operational
of the new access road and the moving approach
of the Ambulance Bays (to be named
in recognition of the grant from the Thank you again for your generous donation and
Coopersmith Trust). Moving the access partnership, which is helping make possible the far-
road and ambulance area was necessary reaching and vital changes that will take place with the
to enable the expansion of the Emergency expansion of the Emergency Department. We wish you
Department itself. The new Ambulance and your loved ones good health and hope that we
Bays and access road of the Emergency will have the privilege of hosting you once again at the
Department , a crucial component of the dedication ceremony following the completion of our
expanded ED, is made possible by the project.
generous gift of the Coopersmith Trust,
which you, Arthur, have facilitated. Best regards,
In May, we received preliminary approval Dr. Shlomi Codish
from the local municipal authority Director General Soroka Medical Center
regarding the construction. We expect to
receive the final construction permit in
September.
In November 2020, the second phase of
the construction and expansion will begin.
It will include the following:
• The expansion of Emergency Department
and Trauma Unit by 2,000 square meters
• The addition of 41 treatment stations
and four isolation rooms in the ER, and two
new treatment stations in the Trauma Unit
Following the completion of Phase Two,