Page 121 - DOE Infrastructure Project List
P. 121
Total Projects
The Eastern Cape Department of Public Works (DPW) is responsible for District Of ces, Early Childhood Development centres, exam centres, special schools, emergencies, fencing, of ce administration and maintenance.
42
Priority area
Total projects
Total value
Planning
7
R218,268,384.78
Early Childhood Development Centres
4
R65,901,476.93
Maintenance
6
R322,104,795.57
N&S: Advanced & full service
2
R96,500,586.21
N&S: Basic Services
4
R197,162,637.45
Norms & standards: New & replacement schools / major works
17
R1,301,303,823.27
Special Schools
2
R238,432,612.81
Value
2,439,674,317.03
Independent Development Trust (IDT) is responsible for Early Childhood Development centres (ECD), Expanded Public Works Programme (EPWP) projects, the building of schools, replacement of mud structures, and special schools.
Total Projects
Priority area
Total projects
Total value
Early Childhood Development Centres
13
R175,776,719.18
Hostels
6
R395,621,170.60
Maintenance
2
R26,448,080.45
N&S: Advanced & full service
2
R180,595,076.88
N&S: Basic Services
2
R4,058,726.18
Norms & standards: New & replacement schools / major works
2
R56,455,051.73
Realignment
1
R5,951,869.66
28
Value
R844,906,694.67
The Mvula Trust (TMT) – a local NGO, takes charge of water and sanitation programmes, sanitation maintenance and operations (dry sanitation) and emergency interventions.
Priority area
Total projects
Total value
Maintenance
1
R26,973,922.36
N&S: Advanced & full service
1
R4,509,961.28
N&S: Basic Services
5
R19,249,756.80
Total Projects
8
Value
R51,665,287.61