Infrastructure projects: Summary of investment per district 2018/19 frastructure projects: Summary of investment per district 2018/19
ALFRED NZO EAST
83 6
Priority area
Total projects
Total value
Early Childhood Development Centres
2
R43,889,885.93
Maintenance
3
R19,272,397.78
N&S: Basic Services
18
R19,610,319.00
Norms & standards: New & replacement schools / major works
1
R97,182,987.09
Realignment
1
R28,155,720.00
Special Schools
2
R5,467,971.52
5
7
4
2
1
Total Projects
27
Investment value
R213,579,281.33
ALFRED NZO WEST
83 6
Priority area
Total projects
Total value
Early Childhood Development Centres
3
R27,921,757.38
Maintenance
16
R90,322,910.16
N&S: Advanced & full service
5
R128,357,397.35
N&S: Basic Services
22
R46,561,082.65
Norms & standards: New & replacement schools / major works
3
R357,211,992.08
Realignment
8
R211,461,968.89
Special Schools
1
R3,522,598.11
5
7
1
4
2
Total Projects
58
Investment value
R865,359,706.61
AMATHOLE EAST
1 7
2
Priority area
Total projects
Total value
Planning
1
R13,099,264.74
Early Childhood Development Centres
5
R99,096,556.33
Maintenance
19
R43,504,870.11
N&S: Advanced & full service
2
R9,325,169.46
N&S: Basic Services
20
R35,296,669.59
Norms & standards: New & replacement schools / major works
5
R310,251,661.95
Hostels
1
R7,977,373.98
5 4
83 6
Total Projects
53
Investment value
R518,551,566.15