Proyecto A     Proyecto B     Proyecto C   Proyecto D
                     Inversion Inicial (ll)  $26,000  $500,000     $170,000     $950,000
                        Año (t)                        Entradas de efectivo
                          1           $4,000         $100,000      $20,000      $230,000
                          2           $4,000         $120,000      $19,000      $230,000
                          3           $4,000         $140,000      $18,000      $230,000
                          4           $4,000         $160,000      $17,000      $230,000
                          5           $4,000         $180,000      $16,000      $230,000
                          6           $4,000         $200,000      $15,000      $230,000
                          7           $4,000                       $14,000      $230,000
                          8           $4,000                       $13,000      $230,000
                          9           $4,000                       $12,000
                         10           $4,000                       $11,000

                   Proyecto A
                   PR=           Inversion/Anualidad
                   PR=                        6.5 Cuatrimestres
                                                                     2.166666667 Años
                                               2 Años
                                               2 meses

                   Proyeto B               $400,000
                                           $280,000
                                           $140,000

                   PR=                       3.875 Trimestral           0.96875 Años
                                              11 Meses                   11.625 Meses
                                              19 Dias                19.01041667 Dias
                                              15 Minutos             0.010416667
                                                                          0.25
                                                                           15 Minutos


                   Proyecto C              $150,000            Hay un faltante de recuperacion por lo que no conviene este proyecto
                                           $131,000
                                           $113,000
                                           $96,000
                                           $80,000
                                           $65,000
                                           $51,000
                                           $38,000
                                           $26,000
                                           $15,000

                   Proyecto D    Inversion/Anualidad
                   PR=                   4.130434783 Quincenales     24.33333333
                   PR=                   61.95652174
                                               2 Meses               2.036926742 Meses
                                               1 Dia                 1.123188406 Dias
                                               2 Horas               2.956521739 Horas
                                              57 Minutos             57.39130435 Minutos