Proyecto A Proyecto B Proyecto C Proyecto D
Inversion Inicial (ll) $26,000 $500,000 $170,000 $950,000
Año (t) Entradas de efectivo
1 $4,000 $100,000 $20,000 $230,000
2 $4,000 $120,000 $19,000 $230,000
3 $4,000 $140,000 $18,000 $230,000
4 $4,000 $160,000 $17,000 $230,000
5 $4,000 $180,000 $16,000 $230,000
6 $4,000 $200,000 $15,000 $230,000
7 $4,000 $14,000 $230,000
8 $4,000 $13,000 $230,000
9 $4,000 $12,000
10 $4,000 $11,000
Proyecto A
PR= Inversion/Anualidad
PR= 6.5 Cuatrimestres
2.166666667 Años
2 Años
2 meses
Proyeto B $400,000
$280,000
$140,000
PR= 3.875 Trimestral 0.96875 Años
11 Meses 11.625 Meses
19 Dias 19.01041667 Dias
15 Minutos 0.010416667
0.25
15 Minutos
Proyecto C $150,000 Hay un faltante de recuperacion por lo que no conviene este proyecto
$131,000
$113,000
$96,000
$80,000
$65,000
$51,000
$38,000
$26,000
$15,000
Proyecto D Inversion/Anualidad
PR= 4.130434783 Quincenales 24.33333333
PR= 61.95652174
2 Meses 2.036926742 Meses
1 Dia 1.123188406 Dias
2 Horas 2.956521739 Horas
57 Minutos 57.39130435 Minutos