Page 43 - ECCS 2019-20 AERR and Three Year Education Plan
P. 43

   Summary of Capital and Facility Projects: ECACS Three-Year Education Plan and Annual Education Results Report
Modern Learning Environments
The project design was developed through the extensive collective efforts of all members of the East Central Catholic School Division Building Committee, the existing St. Thomas Aquinas School staff, Alberta Education, Alberta Infrastructure, and the Design Team. The new school will support an occupancy capacity of 300 students and 27 instructional staff. The design development addresses the current and long-term education vision of the School Board and the School’s Administration and Staff.
All work shall be performed and coordinated to ensure the School is completed for turnover to the School Board November 2021 and opening to students January 2022. The demolition of the existing school and site work will be completed Spring of 2022. Weekly site construction image updates can be accessed from the following link - https://photos.app.goo.gl/fj5GNvLyWVTeenvC8
Estimated Cost - $ 16,671,000.00
    Page 40





























































































   41   42   43   44   45