PROGRESSIVE FREEZE SCHEDULE


    BIM MODEL WORKFLOW








                        20%             40%            50%            60%            70%           80%            90%



      Phase 1         Phase 2         Phase 3        Phase 4       Phase 5         Phase 6       Phase 7        Phase 8       100%SD

      LEVELS &        SITE +          CORE           CORES         PODIUM +        OFFICE        OFFICE         RESI TOWERS +  SD SUBMISSION
      GRIDS           TRACK           GEOMETRY +                   GLASS           TOWERS        TOWERS         SPECIAL
                      OVERBUILD       BASEMENT                     ATRIUM          FACADE                       PROGRAM

      FLOOR LEVELS    SITE AND        BOUNDARY       FINALIZED     PODIUM FREEZE   OFFICE TOWERS   FINALIZED OFFICE   RESIDENTIAL TOWER
      STRUCTURAL      TRACK           OF CORE,       CORE FOR      ATRIUM GLASS    FACADE        TOWERS         FACADE GEOMETRY
      GRID            OVERBUILD       RAMP,          ALL TOWERS    GEOMETRY        GEOMETRY                     DEFINED
                      GEOMETRY        VEHICULAR                    FREEZE          DEFINED
                      FREEZE          PARKING
                                      AND
                                      LOADING
   2   3   4   5   6   7   8   9   10   11   12