Page 35 - Green Builder's Resilient Housing Design Guide 2018
P. 35

CREDIT: UK DEPARTMENT OF INTERNATIONAL DEVELOPMENT  Wipeout. Scenes like this on
            the Caribbean island of Jost
            Van Dyke northwest of Tortola
            were all too common following
            Hurricane Irma’s passage in
            September 2017.











































             ■ Analyzing combinations of energy efficiency and centralized and   partnerships (PPPs); or typical capital improvement loans;
              distributed energy generation options and their impacts on the existing   ■ Supporting the contract negotiation process;
              grid, along with their costs;                         ■ Supervising construction to ensure that best practices and safety
             ■ Identifying existing vulnerabilities in the grid (from disasters, overloads or   standards are implemented;
              other issues), and the opportunities to strengthen the grid.  ■ Commissioning the system with the local island utility, the contractor
              The second step is project identification and resilient development. Once   and a third-party engineer.
            the planning process identifies the possible investment projects, the next   The efforts in all three components are mutually reinforcing. The rapid
            phase of the effort focuses on increasing the investment opportunity in   integrated resource planning work identifies optimal climate resilient projects
            targeted Caribbean islands by creating more-detailed plans and reducing the   to pursue. Project derisking ensures high quality and attractive investment-
            overall risks. The process includes:                    ready projects. Meanwhile, project financing and construction oversight
             ■ Identifying the mix of resources that will meet a specific island country’s   support ensures the rapid quality deployment of these projects—enabling
              needs at least cost and determining the best place to install those   beneficiaries to see the myriad benefits, including lower costs and increased
              resources;                                            reliability and resiliency.
             ■ Performing a detailed financial and economic analysis;  This, in turn, reinforces the value of the integrated plan and the iterative
             ■ Preparing the sites for development and commercialization.   process continues. Moving forward with this process yields faster, higher-
              The third step is project financing and construction. Once resilient,   quality and lower-cost projects, making it possible to accelerate the transition
            renewable projects are developed and considered investment ready, affected   to a stronger, cleaner, more sustainable future. GB
            countries need support in mobilizing concessionary and grant financing and
            private sector capital to turn those proposed projects into steel in the ground.   The Rocky Mountain Institute (RMI) engages businesses, communities, institutions and
            They also need support in supervising construction to ensure safety and   entrepreneurs to accelerate adoption of market-based solutions that cost-effectively
            building standards are met. This support includes:      shift from fossil fuels to efficiency and renewables. Christopher Burgess is director of
             ■ Determining the right financial structures such as power purchase   projects for RMI’s Islands Energy Program (IEP). Justin Locke is the IEP’s director. Stephen
                                                                    Doig is RMI’s managing director.
              agreements (PPAs); build, own, operate, transfer (BOOT); public-private

            www.greenbuildermedia.com                                      Resilient Housing Design Guide GREEN BUILDER MEDIA  35
   30   31   32   33   34   35   36   37   38   39   40