Page 179 - IBC Orders us 7-CA Mukesh Mohan
P. 179

Order Passed Under Sec 7
                                                                           Hon’ble NCLT Ahemdabad Bench

                                     IN THE NATIONAL COMPANY LAW TRIBUNAL
                                                   AHMEDABAD BENCH

                                             C.P. (I.B.) No. 11/7/NCLT/AHM/2017


                                                   Decided On: 09.05.2017

                                             Applicant: Vasanti Petro Chem Ltd.
                                                             VS
                                                    Respondent: Anil Ltd.

               Judges/Coram:
               Hon'ble Sh. Bikki Raveendra Babu, Member (J)

               Counsels:
               For Appellant/Petitioner/Plaintiff: Mr. Arjun Sheth

               For Respondents/Defendant: Mr. Ashish Doshi

                                                          ORDER



               Hon'ble Sh. Bikki Raveendra Babu, Member (J)


               Learned Advocate Mr. Arjun Sheth present for Petitioner/ Financial Creditor. Learned PCS Mr. Ashish
               Doshi present for Corporate Debtor/ Respondent.


               Application is filed by the Financial creditor seeking permission to withdraw CP (IB) no. 11/2017 on the
               ground that there is a settlement between Financial creditor and Corporate debtor.


               The  said  application  is  registered  as  IA  104/2017.  Notice  on  the  application  given  to  the  Financial
               creditor.


               Heard both sides arguments.

               The  petitioner  is  at  the  stage  of  hearing  before  admission.  It  appears  there  is  a  settlement  between

               Financial Creditor and Corporate debtor.

               Financial Creditor is permitted to withdraw the petition. IA 104/2017 is allowed accordingly.


               In view of the order passed in IA 104/2017, this CP (TB) no. 11/2017 is dismissed as withdrawn. No
               order as to costs.