                 FINANCIAL SUMMARY


                                                      FY 15/16       FY 16/17      FY 17/18       FY 18/19
                FUNCTIONAL AREA
                                                      ACTUALS        ACTUALS       BUDGET        ADOPTED
                Electric-Other Expenses                  908,798        904,964         1,200          1,200
                Supervision & Engineering               1,620,999     1,602,976     1,658,967      1,623,839
                Power Generation                         195,552        294,386       324,068        253,236
                Purchased Power                        15,694,473    16,676,093    16,314,143     16,499,878
                Transmission-Substations                  38,926         17,694        75,000         65,000
                Trans & Distribution Lines               989,416      1,151,039     1,147,379      1,162,382
                Maintenance-Street Lights                 19,008         10,680        20,000         22,000

                Maintenance-Meters                          8,395         9,042        15,000         15,000
                Distribution Transformers                 29,172         36,673        35,500         40,500
                Meter Reading                             49,253         61,531        55,043         55,578
                Right of Way Crew                        193,104        178,644       260,398        262,444
                Debt Service                             619,367        321,942     1,434,188      1,454,427
                Transfers                                      0              0     2,579,500      2,543,000
                              TOTAL ELECTRIC FUND      20,366,463    21,265,665    23,920,386     23,998,484


                 SERVICES

               The Electric Department operates and maintains 11 substations, diesel generating facilities and a hydro
               plant. In order to provide reliability to its customers, the  Electric  Department has 2 interconnection
               points with AEP, Mosely Substation and Centerville Substation. Bedford currently purchases wholesale
               power from AMP-Ohio to meet its winter peak demand of 55 MW and summer peak demand of 35 MW.
               The town also generates a portion of its electrical needs at its 5 megawatt hydro facility on the James
               River. The Department currently has 20 highly skilled professionals to operate, maintain and plan for the
               future of its  electrical system.   A state  of the art 3  MW solar generating plant will come  on line in
               January, 2018.

               In conjunction  with the electric service system, the City provides street lighting to various parts  of
               Bedford. The current policy is to provide lights on every other utility pole, and to provide new lights as
               requested. As part of the Downtown revitalization effort, decorative lighting has been installed. The
               placing of utilities underground has also been supported as part of revitalization efforts.