            I) The total investment of 1,566,867 Million Baht in SP2

                    The cabinet resolution on the 7th April 2009 approved 1.567 Trillion Baht of SP2 investment
            programs, prioritizing education sector, public health, telecommunication, logistics, and energy sector for

            72.8% as shown in Figure 1.




            Figure 1 : The 1.567 Trillion Baht of Total Investment in SP2

                                                                                            Infrastructure and
                                      Healthcare                                            increasing quality
                       Education         0.6%        Development of the 5
                         3.8%                          southern provinces                   of lives
                                                            6.4%                            Creative economy
                                                                                            Healthcare
                                                                                            Water resources
            Creative economy                                        Water resources         Tourism promotion
                  1.3%                                                  14.7%               Education

                                                                                            Development of the
             Tourism promotion                                                              5 southern provinces
                   0.4%










                                          Infrastructure and increasing quality of lives
                                                          72.8%
            Source: NESDB



            II) Project screening of 1,435,739 Million Baht
                    From the cabinet resolution on 6th May and 15th June 2009, the project steering committee classified

            the shovel-ready projects for 2009-2012 as below.
                    • Group 1 (Blue): the most readiness projects are able to start their procurement and disbursement

                   within fiscal year (FY) 2009.
                    • Group 2 (Red): the readiness projects commence their operations on FY 2010.

                    • Group 3 (Green): the pipeline projects will commence on FY 2011 onward.