Page 34 - EPC Solution
P. 34

▪  Installation of Civil Work ,Copper Cable and OFC Network
                          ▪  Commissioning Test all installed network
                          ▪  Work Period : Dec 2009 – June 2010
                          ▪  Contract Value : as requested
                          ▪  Customer Rep.
                                        Khun Viwat Puckkoh
                                          Tel. 0 2656 6789


                       ▪  TOT Corporation Public Co., Ltd. , Conduit and Cable Installation for
                           Laksi Monument Bridge in Laksi exchange

                          ▪  Installation of Civil Work ,Copper Cable and OFC Network
                          ▪  Cutover the existing network into newly built conduit
                          ▪  Commissioning Test all installed networks
                          ▪  Work Period : Oct 2010 – June 2011
                          ▪  Contract Value : as requested


                       ▪  TOT Corporation Public Co., Ltd., Secondary Cable Replacement for 8
                           Exchanges, 33 Cabinets in Metropolitan Area 4

                          ▪  Installation of Copper Cable
                          ▪  Cutover the existing network into newly built cable
                          ▪  Commissioning Test all installed networks
                          ▪  Work Period : June 2011 – May 2012
                          ▪  Contract Value : as requested

                       ▪  TOT Corporation Public Co., Ltd., Construction of Underground Conduit
                           and Cable Network in TOT Head Office Exchange

                          ▪  Construction of Underground Manhole and Conduit
                          ▪  Installation Copper Cable
                          ▪  Cutover the existing network into newly built cable
                          ▪  Commissioning Test all installed networks
                          ▪  Work Period : Jan 2013 – June 2013
                          ▪  Contract Value : as requested

                       ▪  TOT Corporation Public Co., Ltd., under contract of Opnet (Thailand)
                           Limited. Ekachai Exchange

                          ▪  Call Through test all existing lines and making cut-sheet
                          ▪  Cutover the existing network into newly built cable
                          ▪  Commissioning Test all installed networks
                          ▪  Work Period : June 2014 – Dec 2014
                          ▪  Contract Value : as requested






                   January 2021                                                                     Page 34 of 37
   29   30   31   32   33   34   35   36   37