Page 14 - Management Accounts Design Feb 2017 v7
P. 14

Capital Expenditure
















                                       MONTH                        YEAR-TO-DATE                  FULL-YEAR
       Description '£(000)
                              Act        Bud       A v B       Act      Bud      A v B    Fc 1+11    Bud      F v B
    IT                         3          0         (3)         3        0        (3)       99        99        0
    Production                 15        80         65         15       80        65        163      163        0
    NPD                        0          0         0           0        0        0         200      200        0
    Other                      1          0         (1)         1        0        (1)       33        33        0
    Building Refurb            29        325       296         29       325      296        338      325       (13)
    Total CapEx                48        405       357         48       405      357        833      820       (13)

                            Awaiting
        Capex Description              Budget
                            Approval
    IT Hardware Refresh        4         20                 Retrospective Capex for IT hardware refresh costs reported
    Plant Maintenance          15         0                 Retrospective Capex for Machine Maintenance Costs reported
    Product Showroom           15        15                 New Showroom fit out costs
    IT Hardware Refresh        10        20                 Re-cabling in Factory, Lab and Quality Office
    IT Hardware Refresh        6         20                 IT AV Costs and Branding






         Capex Overrun        Forc       Bud       F v B
    Building Refurb           413        400       (13)     Building Refurb structural works