EOS          9XXXX-Template layout for gantry’s floor anchors




                   f.  Unlike Part 1, there is only one diameter to be concerned with. There
                      is a total of 8 holes to drill: 4X for the Lateral Generator and 4X for

                      the Gantry frame.

                   g.  They all require 8mm holes (M6 HKD drop-in anchors).

                   h.  When you finish drilling all the holes, make sure you blow out any
                      debris inside the hole.


                   i.   Drive in the drop-in anchors into their respective holes and lock them
                      in using a “prop-in tool”, if available.