Page 147 - Civil Engineering Project Management, Fourth Edition
P. 147

Civil Engineering Project Management
                          132
                          should always be warned when greater accuracy than this must be obtained
                          with concrete. Usually discrepancies of 5mm can be taken up in the floor screed
                          of granolithic or terrazzo ground down to the desired smooth finish. To get
                          tiling accurately laid, small pieces of tile are mortared onto the floor base at
                          intervals across it, their level being fixed precisely to the correct finished level
                          by use of the instrument level. A straight edge is then used to keep the finished
                          tiling at the right level between tile pieces, which are cut off as the work pro-
                          ceeds. There are, however, some experienced tradesmen who exhibit astonishing
                          skill in tiling an area perfectly level given only one level point.
                          12.6 Site investigations


                          Site investigations taken at an early, feasibility stage of a project will seldom
                          be adequate for construction. More site tests will be necessary for individual
                          foundations, etc. British Standard BS 5930: 1999, Code of practice for site investi-
                          gations, acts as a general guide for further site tests, but this needs to be sup-
                          plemented by information contained in other publications as suggested at the
                          end of this chapter. The resident engineer will be expected to have an under-
                          standing of the major principles and techniques of soil mechanics so that he
                          can direct work intelligently. But for specifying tests and interpreting their
                          results, an experienced geotechnical engineer is essential, otherwise mislead-
                          ing assumptions can be made which later lead to serious trouble on a job.
                            There is an ‘art’ as well as a science in deciding what additional site investi-
                          gations should take place when construction is started. Advice from a geotech-
                          nical engineer or engineering geologist should always be sought, but when
                          choosing where to site extra boreholes or trial pits ‘hunch’ and ‘suspicion’ can
                          play a part. A hunch should not be dismissed as unscientific; it can arise from
                          studying the known facts and an apprehension that more needs to be known
                          about some aspect of a situation than is currently known at the time. An exper-
                          ienced engineer will always worry more about what he does not know about
                          below-ground conditions, than what he does know. Thus investigating some
                          suspicion there might be a possible unconformity in conditions below ground
                          can sometimes prove more revealing than gridding an area with boreholes
                          at regular intervals – but not always!



                          12.7 Trial pits


                          Hand-dug trial pits are expensive, take time to excavate and are not always
                          as informative as expected. They do, however, expose a formation so that it
                          can be examined in detail. This may be important if thin layers of weak clay
                          or pre-existing shear zones are suspected below ground. The starting size for
                          a pit depends on the depth it is to be sunk. If required to a depth of 5m for
   142   143   144   145   146   147   148   149   150   151   152