Page 161 - Civil Engineering Project Management, Fourth Edition
P. 161

Civil Engineering Project Management
                          146
                            Under file 37/1 all claims should be numbered, usually in order of receipt. Each claim
                            and correspondence thereon (copied from file 31) should be filed as a separate
                            section with a tabbed index. All claims should be listed at the front of 37/1 and
                            marked with the Subject; and whether ‘Pending’, ‘Rejected’, or ‘Settled’ (in the last
                            case transferred to File 37/2).
                          The above list is only an example for guidance. If need be any file can be
                          broken down into sub-files, for example, 11/1, 11/2, etc. On a small job some
                          files can be merged; on a large job a more extensive system may be required.
                          It is best to file correspondence under the name of the addressee. This way
                          letters do not get mis-filed. Important letters that take time to deal with
                          should be photo-copied so that the original can go straight on file and be kept
                          there, and the copy can be used for working purposes.
                            Several files will be required for dayworks sheets. They pose a special prob-
                          lem which is dealt with in Section 13.9.


                          13.3 CVIs from contractor and instructions to contractor


                          CVIs are  confirmation of verbal instructions (sometimes called ‘CVOs’ –
                          confirmation of verbal orders) sent by the contractor to the RE when some
                          verbal instruction has been given to the contractor as described in Section 17.6.
                          These CVIs raise a number of problems. They should be filed together with the
                          RE’s reply and subsequent correspondence. Usually the contractor will have
                          numbered the CVIs in order. If a dispute arises as to whether any payment
                          is due under a CVI, this should be given a claim number and transferred
                          to the Claims File 37/1.
                            As already mentioned all instructions to the contractor have to be given
                          in writing or, if given orally, confirmed in writing as soon as possible. Major
                          instructions will be by letter, copies being put on File 31; but there are many
                          other day-to-day instructions of a minor nature, such as supplying the general
                          foreman with a sketch of some levels, etc. To deal with these the RE should be
                          supplied with forms that can be used for such instructions. The forms should
                          be A4 size, simply headed thus:
                           A-B-C project
                                         Site instruction          No ..........  Date ...................

                           To: The Agent, Messrs XYZ
                           From: Resident engineer
                                         Subject ..........

                           You are requested…etc.
                           .........................
                           .........................
                           This instruction does/does not constitute a variation of the works.
   156   157   158   159   160   161   162   163   164   165   166