Page 272 - Civil Engineering Project Management, Fourth Edition
P. 272

Civil Engineering Project Management
                          252
                          removed before the mortar layer and new concrete is placed. Usually it is the
                          job of the resident engineer’s inspector to inspect formwork and the cleanli-
                          ness of construction joints before permission is given to the contractor to start
                          concreting. If the contractor runs ‘Quality Assurance’ one of his staff should
                          act as inspector of formwork, but this does not relieve the resident engineer of
                          his need to inspect on behalf of the engineer.
                            In liquid-retaining structures resilient plastic waterstops are usually pro-
                          vided at contraction joints. Fixing half their width in the stop-end shuttering
                          to a narrow reinforced concrete wall often leaves a congested space for the
                          concrete which must therefore be most carefully vibrated in place to ensure
                          that the waterstop is bedded in sound concrete. If the concrete face of the joint
                          is to be bitumen painted before the next wall section is built, bitumen must
                          not get on the waterstop.
                            Floor joint grooves need cleaning out by water jetting, then surface drying
                          as much as possible with an air blower before the priming compound sup-
                          plied by the manufacturer of the joint filler is applied to the groove faces. It is
                          essential that this primer is not omitted, and the filler must be pushed down
                          to the bottom of the groove. Joint grooves are normally filled after the concrete
                          has been allowed to dry out for 2 or 3 weeks when most shrinkage on drying
                          should have taken place (see Section 19.11).
                            Leaks from liquid retaining concrete structures are most likely to occur
                          from opening up of wall joints due to wall movement, especially at the cor-
                          ners of rectangular tanks; and puncturing of the floor joint filler under liquid
                          pressure where the filler has not been solidly filled to the base of the groove.



                          19.11 Concrete finish problems


                          The skill required by carpenters to make and erect formwork for concrete is
                          seldom fully appreciated. The formwork must remain ‘true to line and level’
                          despite substantial loading from the wet concrete. Column and wall faces
                          have to be strictly vertical, and beam soffits strictly level, or any departure
                          will be easily visible by eye. Formwork for concrete which is to remain
                          exposed to view has to be planned and built as carefully as if it were a per-
                          manent feature of the building. Many methods have been tried to make the
                          appearance of exposed concrete attractive: but any of them can be ruined by
                          honeycombing, a bad construction joint, or by subsequent weathering reveal-
                          ing that one pour of concrete has not been identical with adjacent pours, or
                          that the amount of vibration used in compacting one panel has been different
                          from that used in others. If concrete has to remain exposed to public view,
                          then the resident engineer should endeavour to agree with the contractor
                          what is the most suitable method for achieving the finish required if the speci-
                          fication or drawings do not give exact guidance on the matter. The problem
                          is that if, through lack of detailed attention, a ‘mishap’ on the exposed surface
                          is revealed when the formwork is struck, it is virtually impossible to rectify it.
                          Sometimes rendering the whole surface is the only acceptable remedy.
   267   268   269   270   271   272   273   274   275   276   277