A problem for the designer
                                                                  Plate 6a.
                                                                  under the Construction (Design and
                                                                  Management) Regulations 1994 who
                                                                  has to pay ‘adequate regard to the
                                                                  need to avoid foreseeable risks’ (see
                                                                  p. 107 et seq.). The designer may decide
                                                                  a stable berm should be cut into the
                                                                  hillside before the pipe trench is
                                                                  excavated











































                          Plate 6b.  Steel piling sometimes
                          does not go where the civil
                          engineer thinks it has – especially
                          when he was not aware the
                          ground contained boulders or
                          other obstructions