Page 91 - Civil Engineering Project Management, Fourth Edition
P. 91

Civil Engineering Project Management
                          76
                          6.9 Offer by a tenderer to complete early
                          Atenderer may state in his offer that his prices are dependent on being permitted
                          to complete the works in a shorter time than the period for completion stated in
                          the contract documents. This offer must be looked at with care because it implies
                          that other separate contracts the employer may have let for supply of plant to
                          be incorporated in the works must be speeded up also. Similarly any nominated
                          sub-contractors must deliver earlier, and the engineer must be able to provide all
                          outstanding design details according to the shorter programme. It is, of course,
                          a benefit to an employer to have his works completed earlier: it can reduce his
                          capital borrowing charges and enable him to gain an income from the works out-
                          put earlier – though he must be able to accelerate his payments to the contractor.
                          The question that arises, however, is whether the contractor’s shorter time period
                          should be substituted for the period for completion stated in the contract.
                            It is true that speedy construction can maximize a contractor’s profit or
                          permit him to offer a lower price, but this need not be his only motive. A con-
                          tractor may say he can complete a project 3 months early if he suspects the
                          job is so liable to delay by other contractors, nominated sub-contractors, extras,
                          incompleteness of designs or unforeseen conditions, that he runs little risk of
                          having to abide by his promise and indeed may be able to claim extra pay-
                          ment for any delay caused to him.
                            Therefore adoption of the contractor’s time as the contract period for com-
                          pletion needs careful consideration and the position must be resolved clearly
                          before award of the contract. The contractor might have second thoughts
                          about his offer because he would become liable to liquidated damages if he
                          did not complete in the time he offered.



                          6.10 Procedure for accepting a tender


                          After the closing date for tenders, and if tenders have not been publicly
                          opened, contractors will be anxious to discover where they stand: either to
                          prepare themselves for holding discussions over their tender, or to divert their
                          energies elsewhere if they find themselves unlikely to be offered the contract.
                          If prices have not been arithmetically checked, it is inadvisable to give any
                          information lest it turn out misleading. However, when the ranking of tenders
                          has been checked, it should be possible to inform contractors enquiring if they
                          are unlikely to succeed. Once a decision has been made by the employer, all
                          tenderers should be informed by a standard letter, stating the prices received
                          but not identifying the tenderers who submitted them.
                            A valid contract must incorporate three basic elements:
                          • an offer (e.g. the tender) and its acceptance;
                          • consideration (i.e. the contractor undertakes to construct the works and
                             the employer undertakes to pay him for them);
   86   87   88   89   90   91   92   93   94   95   96