Page 3 - KDC's Last 5 Years: Texas
P. 3
CORPORATE TENANT SIZE SCHEDULE STATUS
Independent Bank of Texas HQ 159,000 SF 12 Months Underway (2019 Completion) - 400 Employees
State Farm at CityLine Regional HQ 2,100,000 SF 42 Months Complete - 9,000 Employees
Pioneer Natural Resources HQ 1,125,000 SF 25 Months Underway (2019 Completion) - 2,500 Employees
Liberty Mutual Insurance 1,100,000 SF 26 Months Complete - 5,500 Employees
FedEx Office Headquarters HQ 265,000 SF 12 Months Complete - 1,100 Employees
Raytheon 489,000 SF 15 Months Complete - 1,500 Employees
Toyota Motor North America HQ 2,100,000 SF 30 Months Complete - 7,000 Employees
Epic Deep Ellum 250,000 SF 24 Months Underway (2019 Completion) - 1,200 Employees
Frost Bank HQ 500,000 SF 24 Months Underway (2019 Completion) - 1,700 Employees
State Farm Data Centers (2) 300,000 SF 16 Months Complete - 100 Employees
JPMorgan Chase Regional HQ 1,500,000 SF 21 Months Complete - 6,000 Employees
Baylor Scott & White 300,000 SF 23 Months Underway (2020 Completion) - 1,500 Employees
SRS 100,000 SF 14 Months Underway (2020 Completion) - 500 Employees
TOTAL LAST FIVE YEARS 10,288,000 SF 23 MONTHS 38,000 EMPLOYEES
AVERAGE