Page 3 - KDC Corporate Facilities Portfolio_December 2019
P. 3

CORPORATE TENANT  SIZE          SCHEDULE                                     STATUS                                      TRANSACTION TYPE


 State Farm Regional HQ at CityLine  2,100,000 SF  42 Months      Complete: 9,000 Employees                              NNN Lease / Open Book



 Raytheon at CityLine  489,000 SF  15 Months                      Complete: 1,500 Employees                              NNN Lease / Open Book


 Toyota Motor North America HQ at Legacy West  2,100,000 SF  30 Months  Complete: 7,000 Employees                             At Risk Dev Fee


 Liberty Mutual Insurance at Legacy West  1,100,000 SF  26 Months  Complete: 5,500 Employees                             NNN Lease / Open Book


 JPMorgan Chase Regional HQ at Legacy West  1,500,000 SF  21 Months  Complete: 6,000 Employees                        At Risk Dev Fee / Land Owner


 FedEx Office HQ at Legacy West  265,000 SF  12 Months            Complete: 1,100 Employees                              NNN Lease / Open Book


 State Farm Data Centers (2)  300,000 SF  16 Months                Complete: 100 Employees                                      NNN Lease


 State Farm at Park Center Regional HQ  1,750,000 SF  39 Months  Underway (2020 Completion): 9,000 Employees             NNN Lease / Open Book


 Pioneer Natural Resources HQ  1,125,000 SF  25 Months  Underway (2019 Completion): 2,500 Employees                      NNN Lease / Open Book


 Epic Deep Ellum  250,000 SF      24 Months            Underway (2019 Completion): 1,200 Employees                            At Risk Dev Fee


 Frost Bank HQ  500,000 SF        24 Months            Underway (2019 Completion): 1,700 Employees                       NNN Lease / Open Book


 Credit Suisse  250,000 SF        15 Months            Underway (2019 Completion): 2,000 Employees                            At Risk Dev Fee


 Independent Bank of Texas HQ  159,000 SF  12 Months    Underway (2019 Completion): 400 Employees                             At Risk Dev Fee


 Baylor Scott and White  300,000 SF  23 Months         Underway (2020 Completion): 1,500 Employees                            At Risk Dev Fee


 SRS Distribution  100,000 SF     14 Months             Underway (2020 Completion): 500 Employees                               NNN Lease


 Sammons Financial Group  217,000 SF  16 Months         Underway (2021 Completion): 700 Employees                             At Risk Dev Fee


 TOTAL LAST 5 YEARS  12,108,000 SF  22 MONTHS AVG                      47,700 EMPLOYEES
   1   2   3   4   5   6   7   8