Page 3 - KDC Corporate Facilities Portfolio_July 2019
P. 3

SIZE                SCHEDULE                                      STATUS                                   TRANSACTION TYPE


        159,000 SF              12 Months             Underway (2019 Completion) - 400 Employees                         At Risk Dev Fee


      1,750,000 SF              39 Months            Underway (2020 Completion) - 9,000 Employees                   NNN Lease / Open Book


       2,100,000 SF             42 Months                       Complete - 9,000 Employees                          NNN Lease / Open Book


        250,000 SF              15 Months            Underway (2019 Completion) - 2,000 Employees                        At Risk Dev Fee



       1,125,000 SF             25 Months            Underway (2019 Completion) - 2,500 Employees                   NNN Lease / Open Book


       1,100,000 SF             26 Months                       Complete - 5,500 Employees                          NNN Lease / Open Book


        265,000 SF              12 Months                       Complete - 1,100 Employees                          NNN Lease / Open Book


        489,000 SF              15 Months                       Complete - 1,500 Employees                          NNN Lease / Open Book



       2,100,000 SF             30 Months                       Complete - 7,000 Employees                               At Risk Dev Fee


        250,000 SF              24 Months            Underway (2019 Completion) - 1,200 Employees                        At Risk Dev Fee


       500,000 SF               24 Months            Underway (2019 Completion) - 1,700 Employees                   NNN Lease / Open Book


       300,000 SF               16 Months                        Complete - 100 Employees                                   NNN Lease



      1,500,000 SF              21 Months                       Complete - 6,000 Employees                       At Risk Dev Fee / Land Owner


       300,000 SF               23 Months            Underway (2020 Completion) - 1,500 Employees                        At Risk Dev Fee


        100,000 SF              14 Months             Underway (2020 Completion) - 500 Employees                            NNN Lease


        217,000 SF              16 Months             Underway (2021 Completion) - 700 Employees                         At-Risk Dev Fee

                                22 MONTHS
      12,108,000 SF              AVERAGE                             47,700 EMPLOYEES