Page 351 - B6118-AEW-XX-XX-PP-A-0001_(P19)_Contractors Manual
P. 351

CONSTRUCT





         C3 Shopfitting






         C3.1 Stud Walls

         New studwork walls  to be constructed  from            Wall bottom track to be set 20mm off the floor
         Gyproc MF proprietary system to suit the               level, seated on  a 20mm concrete  particle
         scenario. Stud sizing, centres, fixing details and     board sole plate. Wall boards to be set 15mm
         all other  details should be as manufacturers          off the floor level to avoid capillary action prior
         recommendations contained in The White Book:           to any finishes being installed.


         http://www.british-gypsum.com/~/media/                 Stud wall  boards facing into new presenter
         Files/British-Gypsum/WHITE-BOOK/WHITE-BOOK-            booths should be balance laminate with sealed
         Partition-Wall-Systems-Section.pdf                     PVC edges (to prevent capillary action) ready
                                                                for final graphic decoration.
         All walls to  be  suitably retained  at  the  head
         back to soffit.






















































          C3.1           Stud Walls                          2.0                        09 February 2017