Page 11 - B8773-AEW-XX-XX-PP-A-0003_[P6]_Franchisee Toolkit
P. 11

DPG PM / Acquisitions Surveyor  Franchisee  Principal Designer  Principal Contractor
         (As defined under the CDM Regulations 2015)

 Carry out pre-acquisition site visit and prepare                                             NSC Approval
 report / schedule of condition as required.
 Formulate schedule of recommended
 Landlord’s / enabling works to be completed
 prior to occupation.
 Obtain early utilities information relating to
 electricity, gas and water.

 Monitor and maintain project expenditure   Agreement of project expenditure via            Cost Sheet Approval
 within limits of franchisee cost sheet sign off.  approval of cost sheet(s)

 Organise appointment(s) for surveys and   Provide attendance at site visits by utilities   Ensure client is aware of his responsibilities  Where appointed, provide attendance at
 installation of utilities / connections / meters,   companies as required.  site visits by utilities companies as required by   Instructions
 plus supply contracts (where applicable).   Provide specific H&S advice  franchisee.

 Place orders and organise appointment(s) for  Provide attendance at site visits by BT   Ensure a project brief and key activities are   Where appointed, provide attendance
 surveys and installation of telephone lines.   personnel as required.  issued to the project team  at site visits by BT personnel as required by
                                              franchisee.
 Where applicable:  Agree content of the H&S File

 - Commission an asbestos survey report   Where applicable, liaise with DPG Project   Liaise with the design team and review all
 (refurbishment & demolition)  Manager to close out relevant action points   available pre-construction information.
 from any surveys / reports as required.  Undertake review of preliminary drawings
 - Meet Structural Engineer on site to discuss   (Early Design Review Assessment) and report
 project works. Arrange for provision of   Appoint a Principal Designer in writing  findings to the project team and liaise with
 structural design details and calculations to   the designer prior to the OSBM.
 Architects, Contractors and Building Control.  Comply with all ‘Client’ duties which will fall to
 the franchisee under CDM Regulations 2015.  Advise the Client and Project Team of any
 - Meet Party Wall Surveyor on site to discuss   outstanding surveys/reports for the premises
 project and provide feedback on proposals   Ensure that for all projects:  that are required
 to appointed Architects, Contractors,
 Consultants  - a Principal Designer is appointed  Issue the initial Principal Designer Risk Register
 - a Principal Contractor is appointed
 - Commission CCTV drainage survey (where   - appropriate time and resources are
 not provided by Landlord / Developer).   allocated
 Subject to survey findings and agreed lease   - welfare facilities are provided.
 terms, DPG will action or provide further
 advice to he franchisee in relation to any   In order to familiarise yourself with your
 works required.  responsibilities, further guidance on Client
 duties can be found here.

 Recommend Principal Designer to Franchisee  A checklist is also available here.
 Organise OSBM and arrange access via   Attend OSBM and provide comments on   Attendance at OSBM  Where appointed, contribute to review of   On Site Briefing Meeting
 Landlords / agents / other.  initial preliminary layout  preliminary layout and consider physical
         Complete Early Site Visit Review Report and   constraints of site.
 Present schedule of recommended   Discuss budget costs and agree staged   issue to the project team
 Landlord’s / enabling works to be completed   payment terms with contractor (if present)  Discuss budget costs and agree staged
 prior to occupation for discussion and   Liaise with the architect regarding H&S issues   payment terms with franchisee (see tender
 agreement with franchisee.  identified with the design during the OSBM.  below)
         Design out significant risks and record
         remaining residual  risk on the PD Risk Register

         Advise client on remaining residual design
         risks and information not being provided from
         other designers
 Design & build team / operations to review   Written approval of final preliminary layout   Plan, manage and coordinate the pre-
 layout and offer comments / approval  following OSBM to confirm design freeze.  construction phase relating to all Health &   Prelim Layout Approval
         Safety matters
 Consider Health & Safety at Work Act with
 regard to provision of staff WCs.  Compile the Pre Construction Information

 Consider Equality Act 2010 with regards to   Issue Pre Construction Information to the
 provision of access / inclusive design and   project team
 extent of reasonable adjustments.
         Ensure co-ordination between designers

         Update Principal Designer Risk Register
         Continue process throughout the project                                                               11
   6   7   8   9   10   11   12   13   14   15   16