PEMASANGAN

                                                        PATOK
                                                   PEMBATAS DAN
                                                       ELEVASI

                                                                                            TIDAK

                                                             YA

                                             PEMADATAN SUB GRADE



                                      PENGHAMPARAN SUB BASE COURSE
                                                              YA                            TIDAK



                                                    CEK ELEVASI



                                          PEMADATAN SESUAI LINTASAN

                                                              YA                            TIDAK

                                      PENGETESAN KEPADATAN LAPANGAN
                                                 (CBR - SAND CONE)



                                              PENGECORAN LC K-175



                                          PEMBESIAN TULANGAN RIGID



                                            PENGECORAN RIGID K-350


                                                  PENGUJIAN HWD