Page 71 - 143 Macquarie Street Main
P. 71

   PROJECT DEVELOPMENT AND SERVICES 8.2 Cost Estimate (continued)   DESCRIPTION OF WORKS/FUNCTIONAL USES   GFA   UNIT    RATE - ROUNDED (AU$)    TOTAL (Excl GST)   EOT FACILITIES       Allow for additional showers and locker areas for male & female + bicycle storage to existing EOT facilities including service provisions - assumed similar upgrade as scenario 2. (Note: Scope unknown, allowance of 20sqm) TOILET AMENITIES Refurbishment existing M&F toilet amenities at typical levels Refurbishment existing disabled toilet amenities at ground floor level TOILET PLANT ROOMS Allow for epoxy coated floor finish within plant rooms (Note: Area allowance of 317sqm) $70,000 $576,000 $14,000 $28,530 1   24 Item $70,000        Sub Total - EOT Facilities $70,000        No $24,000       1 No $14,000        Sub Total - Toilet Amenities $590,000          1 Item $28,530        Sub Total - Toilet Amenities $28,530      < CONTENTS > 71                          