Page 73 - 143 Macquarie Street Main
P. 73
PROJECT DEVELOPMENT AND SERVICES 8.2 Cost Estimate (continued) DESCRIPTION OF WORKS/FUNCTIONAL USES GFA UNIT RATE - ROUNDED (AU$) TOTAL (Excl GST) MECHANICAL SERVICES Allow for upgrades of fans, additional ductwork to service expanded EOT facilities Allow to make relevant changes to Basement car park mechanical ventilation systems Allow to remove floor condenser water PAC units Allow for changes to base building ductwork to revert to a standard base building fitout Allow for defit of computer room and changes to condenser water pipework @ L03 Allow for changes to level 12 to suit the standard base building fitout Allow for changes to the BMCS to suit the changes to mechanical, fire system etc $8,000 $5,000 $38,400 $96,000 $3,000 $12,680 $36,000 1 12 Item $8,000 1 Item $5,000 Level $3,200 12 Level $8,000 1 Item $3,000 1 Level $12,680 12 Level $3,000 Sub Total - Mechanical Services $199,080 < CONTENTS > 73