Page 77 - 143 Macquarie Street Main
P. 77
PROJECT DEVELOPMENT AND SERVICES 8.2 Cost Estimate (continued) DESCRIPTION OF WORKS/FUNCTIONAL USES GFA UNIT RATE - ROUNDED (AU$) TOTAL (Excl GST) SITE SERVICES INFRASTRUCTURE Electricity upgrade & Substation contribution Stormwater mains connection & detention tank Sewer mains connection Water mains connection Gas mains connection Fire booster pump assembly & connection Comms/Data connection $40,000 $50,000 $20,000 $15,000 $10,000 $25,000 $10,000 1 Item $40,000 1 Item $50,000 1 Item $20,000 1 Item $15,000 1 Item $10,000 1 Item $25,000 1 Item $10,000 Sub Total - Site Services Infrastucture $170,000 < CONTENTS > 77