PROJECT DEVELOPMENT AND SERVICES 8.2 Cost Estimate (continued) DESCRIPTION OF WORKS/FUNCTIONAL USES GFA UNIT RATE - ROUNDED (AU$) TOTAL (Excl GST) TOTAL CONSTRUCTION BUDGET (Excl GST) 6105 SQM $5,085,555 7.5 % $5,085,555 1 % $5,466,972 % $5,542,963 Design Fees (Excl DA drawings) Authority Fees Contingency Sum GST 10 10 $381,417 $75,991 $554,296 $609,726 $1,260,000 TARGET CONSTRUCTION BUDGET AU$ (Excl GST) $6,097,259 % TOTAL CONSTRUCTION BUDGET AU$ (inc GST) Indicative additional budget for re-building the Lobby AU$ (Excl GST) 6105 SQM $6,706,985 420 SQM $3,000 78