   PROJECT DEVELOPMENT AND SERVICES 8.2 Cost Estimate (continued)   DESCRIPTION OF WORKS/FUNCTIONAL USES   GFA   UNIT    RATE - ROUNDED (AU$)    TOTAL (Excl GST)           TOTAL CONSTRUCTION BUDGET (Excl GST) 6105 SQM $5,085,555        7.5 % $5,085,555       1 % $5,466,972     % $5,542,963   Design Fees (Excl DA drawings) Authority Fees Contingency Sum GST 10 10 $381,417 $75,991 $554,296 $609,726 $1,260,000       TARGET CONSTRUCTION BUDGET AU$ (Excl GST)         $6,097,259      %             TOTAL CONSTRUCTION BUDGET AU$ (inc GST) Indicative additional budget for re-building the Lobby AU$ (Excl GST) 6105 SQM $6,706,985        420 SQM $3,000        78                          