            5.2 Dimensions marking
            The marking of dimensions (Fig. 5) for biodigester unit should be performed prior to start of
            excavation work. The marking is considered as preparation for excavation and construction
            works. An operational area of 3 m width around the digester should be considered, where
            the workers  will use this  area to  achieve the construction works  around  the tank  base in
            order to prepare the structure of the concrete base, i.e. the bottom of the digester.




















            Fig. 5. Marking of dimensions for a biodigester

            5.3 Excavation works
            The depth of digging depends on the specifications of the soil. The inclination of the sides
            should be 30 cm for each meter depth for the cohesive soil, 60 cm to one meter for the light
            soil, and 90 cm for the sandy soil.