Presidential  Decree  (PD)  269  which    The Renewable Energy Act (RA9513)
                   mandates an EC not only to distribute     under  Sec.  6  of  Article  III  also
                   and sell, but also to generate power.     encourages  all  stakeholders  in  the
                                                             power industry “to contribute to the
                                                             growth  of  renewable  energy
                                                             industry of the country.”

                                                             And lately under the NEA Reform Act
                                                             (RA 10531), specically paragraph (j-
                                                             1) of Sec. 16 in Chapter III, ECs are
                                                             authorized “to construct, acquire,
                                                             own,  operate,  and  maintain
                                                             generating  facilities  within  its
                                                             franchise areas.”

                                                             Finally,  on  October  23,  2019,  the
                                                             Department of Energy (DoE) granted
                                                             BENECO  a  Hydropower  Service
                                                             Contract  (No.  2009-10-30)  for  Man-
                                                             asok. After securing the needed FPIC
                                                             [Free  Prior  and  Informed  Consent]
                                                             from  the  BADANG  IP  [Indigenous
                                                             People's] Group and approval from the
                                                             local  government  units  (LGUs),  the
                                                             project  broke  ground  in  November
                                                             2016. Construction began a year later.

                                                             However, meeting legal requirements
                                                             was  the  least  of  Beneco's  concerns
                                                             when  it  decided  to  go  into  self-
                                                             generation.