                                  Fase Proyek                              Perkiraan Penyelesaian
               General Requirement
               Set up task force                                  Dec 2018
               Network optimization analysis                      Jan – Mar 2019

               RFI Stage
               Preparation & evaluation structure                 Dec 2018
               RFI submission period                              Jan 2019 (W2)
               Evaluate RFI proposal                              Jan 2019 (W3)

               RFP stage
               Prepare RFP document                               Feb 2019
               RFP submission period                              Feb 2019 (W4)
               Evaluate RFP proposal (incl presentation,
               clarification, site visit)                         Mar 2019
               Final negotiation pricing & SLA                    TBD
               Prepare for award                                  TBD

               Implementation stage
               Prepare contract                                   TBD
               Prepare for go-live (bispro update)                TBD
               Prepare for implementation stabilization           TBD