Page 227 - Bahrain Gov Annual Reports (II)_Neat
P. 227

15
                                 Public Works.

              The sum allocated to Public Works in the 1358 budget was Rs. 7,70,600, the
        actual expenditure was Rs. 6,35,300. Of this amount, Rs. 5,01,000 was spent on works
        which were included in the budget, and Rs. 44,000 on new work approved and
        sanctioned during the year but not provided for in the budget.
              In most cases the expenditure exceeded the estimated amount but this was
        frequently due to additions to and extensions of the original plane, especially in
        the case of the hospital buildings and the pier extensions.
              1. Mannmah-Muharraq Swing Bridge. Rs. 59,463.
              The contract was made during the current year. A sum of Rs. 3,00,000 was
        provisionally included in the budget before it was known how much the bridge
        would cost. The contract price was Rs. 3,82,000 of which Rs. 59,000 was paid
        during 1358.
              A sum of Rs 35,000 was budgeted for extending the two ends of tho sea-
        road to the pier terminals. The woik was done by the Manamah and Muharraq
        municipalities and the cost was Rs. 61,376. Each side cost approximately the same
        amount.
             2. Hospital Buildings. Rs. 2,35,000.
              The amount provided in the budget was Rs. 2,57,000. The dispensary was
        entirely completed, the women’s hospital and staff quarters were almost finished,
        and considerable progress was made with the men’s hospital. Foundations of the
        administrative building were finished and various additional buildings, such as
        boiler house etc., were completed.
             The cost of building was very much more than was estimated owing to the
       need for deep foundations : in part of the ground it was found necessary to build
       twelve feet deep before reaching solid ground. The work which is still to be done
       consists of completion of men’s hospitals, the administrative block which includes
       operation theatre etc., and various walls and outhouses.
             Manamah Pier extension. Rs. 1,01,588
             The explanation of the additional expenditure and work is given under Public
       Works Department.
             Pier Trolley Lines. Rs. 16,718.
             The trolley lines were purchased and the old lines repaired but new lines have
       not yet been laid.
             Fort. Rs. 29,070.
             Rebuilding the N. E. tower waB not completed at the end of the year. The
       eastern wall was rebuilt, a new barraok room was constructed also a kitchen and
       a moss hall. The main entrance and guard room were repaired and re-roofed and a
       light roof was erected over the bathing tank.
             Education Department. Rs. 3,998.
             Two additional rooms were added to the Manamah boys’ school and another
       room and a yard were built at the western end of the Technical Sohool.
             Transport Department. Rs. 12,379.
             The expenditure includes the cost of one large additional garage and two
       flats above the Transport Building. The flats are ocoupied by tho staff of the
       Eleotrio Department.
            Passport Office. Rs. 13,416.
             The existing passport office was converted into a Post Office and let to the
       Indian Postal Department, and a new Passport Office was built at the western end
   222   223   224   225   226   227   228   229   230   231   232