Page 387 - Bahrain Gov annual reports(V)_Neat
P. 387

43
                 Electrical Wireman’s Licences were issued to the following wiremen who had been
              successful in passing the Department's Tests.
                    1.  Abdul Rahman Khalifa
                    2.  Yacoob Noor Mohd
                    3.  Ahmen Abdulla
                    4.  Rajput
                    5.  Ali Ebrahim
                    6.  Ali Ashoor
                    7.  Abdulla Ahmed Kooheji
                                                                                             i
                    8.  Mir a Haji Saied
                    9.  Hussain Ismaili
                   10.  Abdul Rahim Abdul Karim
                   11.  Salman Ahmed
                   12.  Jassim Hassari



          Constant routine maintenance of all Government electrical installations was successfully
       maintained during the year. Mr. W. Taylor (Installations Engineer) resigned his post and left
       the Department on the 18th July. His successor, Mr. Manning, arrived on the 4th August but
       he, unfortunately, did not prove satisfactory and he resigned on the 31st October.


          The Gas/Electricity Project. The generating sets installed in Manama “B” Station
       commenced regular operation on natural gas and 7 per cent, diesel oil on the 8th January and
       they continued to operate successfully throughout the year. On this successful performance
       they were accepted as Dual/Fuel engines at the year’s-end and negotiations were continuing
       for a settlement of the Departments claim regarding the inability of the Contractors to supply
       the machines specified.
          The scheme for supplying certain villages was 99 per cent, complete at the year’s-end.


          Future Prospects. A start was made in December on the extension of Manama "B”
       Power Station where the first of three 6,000 k.w. Gas Turbines is to be in commission for
       April, 1958. Reorganisation of the Department’s accounting and billing arrangements will be
       undertaken early in the coming year.



















                                                                                           !