Concept Design  7.5   Concept information required for SuDS evaluation

           The information required at the Concept Design stage will depend on the type
           and scope of the proposed development.


           7.5.1   Pre-application discussion
                                                                 Constructive discussion between the LPA,
                                                                 the LLFA, Thames Water and the SuDS
           The design team will provide a Concept
                                                                 designer will save the developer time and the
           Design for a pre-application design meeting,
                                                                 cost of potential re-design, providing
           or as preliminary design information should a
                                                                 planners with reassurance that the project
           pre-application meeting not be appropriate.
                                                                 that is delivered will meet local planning
           Pre-application discussions with the LPA and          expectations.
           LLFA provide an opportunity for the designer
           to confirm the preliminary requirements for
           the SuDS design, and for the evaluation team
           to understand the objectives and character            The discussions will be informed by the ASA

           of the SuDS proposed for the development.             (Association of SuDS Authorities) NSTS for
                                                                 Sustainable Drainage: Practice Guidance.




                                                                  http://www.susdrain.org/files/

                                                                  resources/other-guidance/lasoo_non_
  49                                                              statutory_suds_technical_standards_
                                                                  guidance_2016_.pdf
           A sunken SuDS courtyard with solar water feature
           into a formal rill at Bromsgrove Civic Centre.         (ASA were formally known as LASOO)